Set Resource Scheduling (Cascade/Gantt Charts and RHs)
To do this, you will have to alter the original Cascade Diagram so that no more than the set number of resources are being employed at any one time.
Example:
This is the original Cascade Diagram:
Example:
This is the original Cascade Diagram:
This is for the case that only 5 workers are allowed:
This is for the case that only 6 workers are allowed: